lafitte-greenway-map1 Placement of the asphalt portion of the Lafitte Greenway bicycle and pedestrian path is now 75% complete in Areas 2, 3, 4, and 5. The Department of Public Works construction contractor, Durr Heavy Construction, has completed installing most of the trail lighting fixtures in Areas 3 and 4, and continues installation of trail lighting in Areas 2 and 5. Lighting wiring will be installed toward the end of the project construction, when the project is ready for public use.

The bicycle and pedestrian roundabout at N. Jefferson Davis Parkway is now complete.

The contractor has completed collecting the cobblestones that will line the Carondelet Walking Path. The contractor will begin constructing the walking path, which will run along Lafitte Ave., in the next two months.

Please note the N. Lopez St. pedestrian bridge is closed and will remain closed for the duration of construction in Area 3.

Please note the N. Rocheblave St. pedestrian path is now closed and will remain closed for the duration of construction in Area 4. A new, paved N. Rocheblave walk, will be constructed as part of this project. Please use N. Galvez or N. Broad streets during construction and avoid entering the construction site.

In the next two months, crews will begin demolishing the sidewalk on the uptown side of Lafitte Ave. The new Carondelet Walking Path on the interior of the park will replace the old sidewalk. Crews will also soon begin replacing the sidewalk on the uptown side of Lafitte Ave. between N. Rocheblave and N. Dorgenois streets. Crews will begin replacing sidewalk on both sides of N. Galvez St. shortly. Please use the temporary walking paths on N. Galvez St. during sidewalk construction.

Durr Heavy Construction continues final grading of Areas 2, 3, 4, and 5.

The overall project is about 50 percent complete and on schedule to be opened to the public in early spring 2015.

To expedite construction, Durr Heavy Construction has divided the Lafitte Greenway project into six sections:

Area 1 – N. Alexander St. to N. Carrollton Ave.

Area 2 – N. Carrollton Ave. to Jefferson Davis Pkwy – currently under construction

Area 3 – N. Jefferson Davis Pkwy to N. Broad St. – currently under construction

Area 4 – N. Broad St. to N. Galvez St. – currently under construction

Area 5 – N. Galvez St. to N. Claiborne Ave. – currently under construction

Area 6 – N. Claiborne Ave. to Basin St.

Please use caution when driving, bicycling or walking near active construction sites. Traffic cones, construction fencing and safety signage are in place to keep everyone safe. Please respect the signage and fencing – do not enter active construction sites.

Thank you for your continued patience.

Cheryn Robles, APR

Community Outreach Specialist

Department of Public Works